Royal Hall Supplemental Study
Preferred Strategy: Key Characteristics
1.0 OBJECTIVES
1.1 The key components of the strategy which the Design
Team and the Study Management Group have devised have been
based around four key criteria:
- carrying out essential structural repairs and waterproofing;
- maximising public access and usage;
- providing a basis for further restoration work as and
when funds become available;
- containing risk and the possibility of the contract
costs overrunning.
2.0 LIKELY SHAPE OF THE SCHEME
2.1 This approach and the budget limit (which cannot be
exceeded) gives a scheme which, subject to further detailed
design and costing analysis, is likely (but not certain)
to contain the following:
- a repair of the structure across all of the building,
including the front pediment and the rear ambulatory area;
- weatherproofing and a rainwater strategy which will
prevent future water ingress;
- a basic level of heating and ventilation which will
overcome the systemic condensation problems experienced
for much of its life;
- works to the rear of the stage to allow stage to be
used again;
- improved access for those with disabilities to the
north and south corridors, grand circle and stage;
- improved toilets and first aid accommodation;
- new seats in the Grand Hall and Grand Circle;
- limited interpretive heritage displays for public
and educational use;
- decorative repairs only throughout front-of-house areas.
2.2 These works, if achievable within the budget, will allow
the building to be used for the following:
- access to the Grand Hall and Grand Circle for stage
performances;
- access to these and the north and south corridors;
- access for public viewing of the main auditorium, foyers
and Grand Circle;
- access to the stage for productions similar to those
pre-2001;
- re-use of the basement dressing rooms, though with only
limited facilities;
- possible public access to the ambulatory, though possibly
only limited access to the rear terrace;
- public viewing of an interpretive heritage display which
traces the history of the building.
2.3 It is expected therefore that the building will be
reusable once again for community type entertainment and
arts purposes, for conferences and for commercial entertainment.
Additionally, the building should be open for the public
to view over most of the ground floor area.
2.4 If there are early cost overruns or tender prices exceed
expectations, the order of priority of works, to stay within
the budget, will be:
(a) Structural repairs and weatherproofing
(b) Access for the Grand Circle and Grand Hall
(c) Enabling of the stage
(d) Access to the rear ambulatory
and not all of these therefore would be achieved if costs
prove more expensive than forecast
2.5 The preferred strategy will not however allow, at this
stage, the following:
- any access to or use of the upper circle (except technical
crew). This will mean the capacity of the hall is reduced
at this stage to c800 (cf 1,200 pre-2001);
- (The strategy does however envisage the provision of
a lift shaft which will enable subsequent restoration of
the upper circle and heritage lounge should funds become
available at a later date.)
- an enlarged Stage House, with little or no possibility
that this will be possible at a future date;
- permanent bar; the use of bottle bars on the north and
south corridors will be necessary as a substitute;
(The installation and reintroduction of a period bar is
likely to be a possible discrete subsequent project.)
- improvements to access, layout and efficiency of the
basement rooms;
- authentic redecoration of the auditorium and other front-of-house
areas;
(A possible further restoration project as an when funds
are made available.)
- re-introduction of period seating;
- widening of the stage performance offering (eg: opera).
3.0 DEALING WITH RISK
3.1 The approach to risk management has assumed higher profile
because of the necessarily limited scope of the revised study.
The risk allowance presently built into the budget totals £1.63m.
This is c31% of the construction budget including preliminaries.
Further work on the risk register to isolate and mitigate
risk further will take place during the next few weeks as
the strategy is turned into a realistic second stage submission
for the Heritage Lottery Fund (HLF).
4.0 PROCUREMENT
4.1 Work has been carried out on developing an appropriate
procurement path. An effective means of procuring a contractor
can in itself help to mitigate risk. A two-stage tender process
is being developed in order to allow the early appointment
of a contractor to feed a “buildability angle” into
the final stages of the design process. If the contractor
is familiar with the scheme proposals and the context in
which they must be implemented, it will improve the scope
to provide greater cost certainty. The procurement path also
envisages an open book arrangement, with the Council having
full opportunity to vet any and all subcontractor appointments.
4.2 A further step being developed is to tender the scope
of works on an incremental basis, with initial packages being
sufficiently large to ensure that a contractor can achieve
economies of scale but with sufficient reserve to cater for
any cost increases during construction above and beyond the
project contingency.
5.0 PROGRAMME
5.1 A provisional project programme has been devised, the
key milestones being:
2004
- October: preferred strategy agreed
- October/November: informal discussions with user groups
- 18th November: Final draft proposal for consideration
by Council and HLF considered by Study Management Group
- 26th November: Draft HLF report issued
- Mid December: consideration by Council
- December 24th: submission of revised Stage 2 bid to
HLF
2005
- Late January 2005: HLF Trustees meet to consider revised
submission
- April 2005: tenders issued
- May 2005: Contractor appointed
- September 2005: Stage 2 tender agreed
- October 2005: start on site
2007
- January 2007: commissioning
- March 2007: formal opening
|